четверг, 10 декабря 2020 г.

New russian cruise missile - izdelie 506 / Kh-BD

A few days ago, state tests of a new cruise missile could be completed. GosMKB "Raduga" from 2013 was developed new strategic cruise missile according OKR "Romance" (development project). As we understand now this is missile "izdelie 506".

In 2016 began work on a component of the carrier for new missile - project "506-Tu". This can be the equipment complex of the future missile carrier - this can be Tu-160M (70M). As of 2017, the following test program for "izdelie 506" is planned: 
- first flying tests starting from 31.01.2018
- fullfill flight tests starting from 31.05.2018
- state tests from 28.02.2019 to 30.11.2020

Kh-101 missile (from Militaryrussia.ru, tnx)


On February 23, 2017, the scientific director of GosNIIAS, Evgeny Fedosov, said in an interview that the project of the modernized Tu-160M2 aircraft included a promising long-range cruise missile (code name X-BD). Based on this, it can be assumed that as of 2017, work is underway to formulate requirements and determine the appearance of a new rocket. The range of the new missile will significantly exceed 3000 km - the range of the Kh-101.

According to Fedosov: "Today, a concept has emerged: do not introduce long-range aircraft into the enemy's air defense zone. It (the carrier aircraft) must work outside this zone, and the weapon enters the zone. If such an aircraft carries a lot of weapons, then the information principle starts working again Degradation at enemy air defense. Without entering the enemy air defense zone, but by launching a missile there, we dictate the direction of the strike, moment and density. And if you reconnoitre the enemy air defense well, then we will always find a bottleneck and throw a grouping into this throat. about a strategic nuclear strike, then at least one missile will always pass. And that will be enough ".

The rocket power system uses two types of batteries - chemical thermal HIT-715 developed and manufactured by ZAO NIIHIT-2 and 9I-1550 developed and manufactured by NPP Kvant.

Control system and guidance - probably the Kh-BD will be equipped with an inertial control system using on-board computers with correction according to digital reference maps of flight correction areas using data from a laser (optoelectronic) altimeter or an optical image of the terrain. In the final phase of the flight, an optical or radar correlation seeker may be used.

The engine of missile is a small-sized turbojet engine "izdelie 37B" developed and manufactured by Saturn corporation. Fuel - kerosene TS-1, Decilin and Decilin-M (the main type of fuel). Probably, missiles with different combat equipment use different types of fuel.

Data of missile:
Length - less than 10 m
Case diameter - no more than 0.8 m
Operating range - more than 3000 km (presumably at least 5000 km)
Flight speed - less than 1M

Combat equipment: a conventional warhead for a rocket is being developed by GosNIIMash. According to the annual report of GosNIImash for 2016, working design documentation, production of materiel and testing of the BS-506 warhead are being developed.

We don't have any other information now but thinking that in the nearest future we all will know more about this interesting and secret missile.

Thanks for all sources and attention!

воскресенье, 13 сентября 2020 г.

9M79 Tochka launch from Belorussia VoenTV

9M79 Tochka launch from Belorussia VoenTV

09.09.2020 belorussian army's TV "VoenTV" published video with launch of 9M79 missile "Tochka" SS-21 SCARAB (not "Tochka-U"). In this video was used mod. 9M79F with warhead 9N123F. Interesting that CEP of missile was near 36 meters and radius of total damage of warhead was near 42 meters. Also very interesting that old missile 9M79 can fly.

TEL 9P129M Tochka with missile 9M79

Launch of belorussian 9M79 Tochka

    




Yours Missiles Underground

понедельник, 7 сентября 2020 г.

First ejection test of Sarmat ICBM

First ejection test of Sarmat ICBM

update - as wrote MilitaryRussia.Ru this is not Sarmat - this is UR-100UTTkH - you can see note about this at MilitaryRussia. 

In december of 2017 at Plesetsk missiles test center was first ejection test of Sarmat large liquide ICBM. Designarion of this ICBM in Russia is "128 complex" or missile 15A28. Main developer is Makeev State Rocket Center (at Miass, Ural).

Russian ecologists have completed a full cycle of work on reclamation and restoration of nature in the place where the first Sarmat ICBM down.

Stage of Sarmat ICBM, december 2017 (ecologists site)

Mi-8 of ecoligists group at the place of Sarmat ICBM test, december 2017 (ecologists site)





воскресенье, 6 сентября 2020 г.

Google Maps vs Sarmat ICBM

Google Maps vs Sarmat ICBM

Time and power. Power and time. And Google Maps can place in shadow russian Sarmat ICBM testing place at Plesetsk missiles test center. Let's see this. May be not special of course but I think "by order" from russian special services.

ICBM RS-28 Sarmat test site - ESRI Maxar Maps (2019-2020)

ICBM RS-28 Sarmat test site - ESRI Maxar Maps (2019-2020)

ICBM RS-28 Sarmat test site - Bing Maps (2018-2019 may be)

ICBM RS-28 Sarmat test site - Google Maps (2014 !!!) - and thats all...

Yours Missiles Underground



четверг, 13 августа 2020 г.

SS-X-30 SARMAT - RS-28 Sarmat

SS-X-30 SARMAT - RS-28 Sarmat
complex 15P128 or 15P228, missile 15A28


upd.11/09/2020

Heavy liquide intercontinental ballistic missile - missile for replacement of the RS-20 / R-36 / SS-18 SATAN ICBMs. 

Launch tube with ejection-test version of ICBM RS-28 Sarmat (test-site Plesetsk before launch 27.12.2017, http://mil.ru)



























Developers:
- Makeev GRTs (State Rocket Center, Miass, the lead developer)
- NPO Mashinostroyenia (Reutov)
- NPO Energomash (engines)
- KBSM (launch equipment)
Some of reserchers had idea about possibility of cooperation with Yuzhnoye Design Bureau (Dnepropetrovsk, Ukraine) - it was possible before 2014.

Developing: first information about development of Sarmat was published at 2009. The terms of reference for the development of ICBMs was approved in 2011 and the technical development for the "Sarmat" was begin in 2012.

Tests: first ICBM Sarmat for ejection tests was ready from industry at november 2015 but with several different reasons first launch was delayed to 2017 - engines, truobles with pant, not ready test-site. Media wrote in 2017 that to the end of year plant must build three missiles for ejection tests.   

Launchs list of Sarmat missile:
01-ejection - First ejection test (one of three) - mod. RS-28 Sarmat for ejection tests - test-site Plesetsk Yubileynaya site (silo) - 27.12.2017
history of plans (special feature of russian planning):
june 2015 (early 2015)
autumn 2015 (26.06.2015)
17-31.12.2015 (16.12.2015)
march 2016 (january 2016)
april-june 2016 (20.02.2016)
second half 2016 (11.05.2016)
march-april 2017 (13.01.2017)
end of june 2017 (01.04.2017)
october-december 2017 (october 2017)

02-ejection - Second ejection test (two of three) - mod. RS-28 Sarmat for ejection tests - test-site Plesetsk Yubileynaya site (silo) - 29.03.2018

03-ejection - Third ejection test (three of three) - mod. RS-28 Sarmat for ejection tests - test-site Plesetsk Yubileynaya site (silo) - may 2018 (ref).

01 - First flight test - real RS-28 mod. - test-site Plesetsk Yubileynaya site (silo) - not now (august 2020)
history of plans (special feature of russian planning):
first half 2016 (2015)
second half 2016 (20.02.2016 г.)
forecast - 2017-2018 (12.05.2016 г.)
forecast - 2018 (07.09.2016)
forecast - 2019-2020 (2018) 
forecast - end of 2020 (2020)


Yubileynaya test-site at Plesetsk with process of loading Sarmat at his silo


Production of Sarmat missiles was established at main plant of Makeev produce cooperation - Krasnoyarsk Machinebuilding Plant. Contract to produce firsts Sarmats was begin in 2011. And in 2014 production was begin.

Employment of Sarmat ICBM will begin at 2021 at Uzhur (Krasnoyarsk region) RVSN division (as we know now at 2020) and later at Dombarovsky. But in 2015 they said about employment in 2018. My forecast for now - 2023-2025. 

19.11.2019 Ru MoD said that all works for emplayment will be finished at 2021 (ref).

Launch equipment: silo launch complex 15P728 similar to silo compexes for heavy ICBMs like R-36M / R-36M2 SATAN. Developer - KBSM.

Transportation-loading vehicle 15T526. Developer - KB Motor TsENKI.

Upper part of transport-launch tube of Sarmat ICBM

Reloading ICBM Sarmat from train to transportation vehicle 

Transportation-loading vehicle 15T526

Missile 15A28 Sarmat
Three stages missile with liquide engines. At first stage used engine similar to 15D285 for SATAN ICBM. Similar liquide engines used at second and third stages.


Guidance: autonomic inertial guidance system with most modern hyroscop system.

Technical data of Sarmat missle:
Length - 32 m
Diameter - 3 m
Start weight - 200 000 kg
Payload weight - 10 000 kg (with upper stage for MIRV/MARV)
Range - 11 000 km
CEP - 100-150 m

Payload:
1. 10-15 MIRV's with several devices of anti-ABM complex
2. 3-5 MARV like object 4202 / 15Yu71












First ejection launch of Sarmat missile at Plesetsk, 27.12.2017.










Second ejection launch of Sarmat ICBM, Plesetsk, 29.03.2018


Main special source Militaryrussia.ru - thank you!
Yours Missiles Underground

понедельник, 10 августа 2020 г.

Russian ICBM staff (2020)

 Russian ICBM staff (2020)

Estimation staff of russian ICBM at the end of 2020

R-36M2 SATAN - 46 missiles (each 10 middle MIRV)
RS-12M Topol - 27 TEL with missiles (mono RV)
RS-12M1 Topol-M - 18 TEL with missiles (mono RV 1Mt-class)
RS-12M2 Topol-M (silo) - 60 missiles (mono RV 1Mt-class)
RS-24 Yars - 101 TEL with missiles (each 6 light MIRV)
RS-24 Yars (silo) - 18 missiles (each 6 light MIRV)
RS-24 Yars-S - 32 TEL with missiles (each 3 middle MIRV)
UR-100HUTTkH Avangard - 2-3 missiles with type 4202 AGBO



Yours Missiles Underground

And about Sarmat (part II)

Engines According to the already known data on the Sarmat rocket, the development of engines for the first stage is carried out by NPO Energ...