Показаны сообщения с ярлыком ICBM. Показать все сообщения
Показаны сообщения с ярлыком ICBM. Показать все сообщения

четверг, 6 января 2022 г.

And about Sarmat (part II)

Engines

According to the already known data on the Sarmat rocket, the development of engines for the first stage is carried out by NPO Energomash named after academician V.P. Glushko (annual report for 2012). The use of the modified propulsion system of the first stage of the R-36M2 Voevoda 15D285 (RD-274) rocket looks quite logical and would save time. The only problem was that the serial production of 15D285 engines in the early 1980s was deployed at PO Yuzhmash, which has now become Ukrainian. And therefore, the production of the newest reincarnation of the Voevoda engines - the PDU-99 / "product 99" propulsion system was entrusted to PJSC "Proton-PM" ("Perm Motors", Perm). In 2013-2016. production of the first engines begins there, and on June 9, 2015, the first debugging firing test of the prototype “product 99” rocket engine took place at the firing stand.



And then further, it is quite likely that there will be problems in setting up the serial production of such a new product. Failure to deliver the first stage engines on time was considered by many experts to be one of the possible reasons for the delayed inrush starts. As you know, during the years 2017-2018. three missile launches not only made a mortar launch from a silo launcher. but they also turned on the first-stage engines - accordingly, already in the course of the throw-in starts, operable engines and a control system for them had to be supplied. At least for the first stage.

Now, for flight tests, it is required to supply not three sets of engines, but twice as many and capable of working not for a few seconds (the duration of the active section during throwing starts), but for    standard tens of seconds. It is likely that the task turned out to be more difficult than it seemed earlier and the production could not cope with this task.

However, I may be wrong - the secrecy of information gives rise to the need to make assumptions. I apologize in advance to the engine builders if it's not about them.















In general, NPO Energomash and Perm Motors have a rather strange relationship - they are, as it were, partners in the production of rocket engines. But for some reason, in 2014, Proton-Perm Motors OJSC collects from NPO Energomash as much as 32 million rubles in penalties under contracts from 2008 and an additional agreement from 2012, and later, already in 2019, on the contrary, NPO " Energomash ”is trying to recover from JSC“ Proton-Perm Motors ”already 33 million rubles of penalties for the allegedly undelivered machines, which, by the way, were nevertheless delivered, but with some delays due to the unavailability of the site for their placement. The court rejected the claims of “Energomash” and satisfied only 2.7 million rubles of the penalty. A strange relationship for strategic partners. I suspect that all this could affect those projects that were carried out by this cooperation of enterprises.


Control system

No one modern missile can't fly without a control system - launching all systems, leaving the launch pad or silo, working and stopping the engines of two stages, separating and working of the upper stage, adjusting the velocity vector of each warhead and finally its compartment - this is responsible for this. control system.

Previously, it was believed that the control system for "Sarmat" is being developed by the Scientific and Production Center of Automation and Instrumentation named after Academician Pilyugin, who is the author of the control systems for launch vehicles "Zenith", "Proton-M" and "Topol-M". But a study of the arbitration cases of Russian courts suggests that the main developer of the control system looks like a different one. This is the Scientific and Production Association of Automation named after Academician Semikhatov.



And, apparently, there may be problems with the control system of the new intercontinental missile. On June 7, 2021, a meeting of the Arbitration Court was held in St. Semikhatov to the Research Institute of Command Instruments. The essence of the claim is the requirement to fulfill the obligations of the research institute for the supply of a set of command devices (KKP) and a block of angular rate sensors (RCS), which should have been supplied initially (under the 2015 contract) on December 31, 2016. By an additional agreement of 04.24.2019, the delivery time was changed to September 2019.In October 2019, not having received the desired NPO Automatics, it went to court.

Command instruments are an indispensable part of a modern ICBM control system. With their help, the aiming of the rocket is carried out before launch - the azimuth of the course is set, the rocket receives all the information necessary for guidance. In the general case, the block of angular velocity sensors is also an absolutely necessary component of the control system - this block determines the behavior of the rocket in flight in an unsupported environment - according to the turns and accelerations that it measures. Relatively speaking, this is the cerebellum of a modern rocket.

So, what about the command instruments and the sensor unit? They were assembled and delivered by the performer, although with a delay in time, but they were! 11/16/2019 But the supplied equipment had drawbacks about which the research institute had warned in advance. Indeed, on January 28, 2020 NPO Automatics by letter of proinfThe Institute was informed about the negative result of the acceptance tests of the KKP. After the corrections, the complex of command devices was nevertheless adopted by the NGO, but only on 04/12/2020. And the most important thing: the courts took into account that the parties agreed on a joint decision of 06/09/2020 due to the fact that during the development of the complex of command devices (PSC) on To the technical task for the mid-range of the ROC “Development of a complex of command instruments of the on-board equipment of the control system on the topic“ 001 ”The Institute achieved accuracy characteristics with a deviation from individual requirements of the technical task for the PAC, due to the lack of a domestic element base with the necessary characteristics.


Apparently, for the whole of 2020 and possibly part of 2021, the performers were finalizing the equipment to meet the requirements of the technical task.It is still unlikely that the Strategic Missile Forces of Russia would want to get the most powerful rocket in the world with accuracy indicators 40 years ago. The Strategic Missile Forces are hardly interested in repeating "Voevoda" - they need a better rocket!


Upgrade from the Voenno-boltovoy channel (05 jan 2022, I quote):

This is not the first time in the course of court proceedings, details of the development of advanced weapons have been disclosed. In cases No. A56-8333 / 2020 (https://kad.arbitr.ru/Card/8b8c115c-1982-4e2c-96d2-b98301377429) and A56-46672 / 2021 (https://kad.arbitr.ru/Card / 4dee6d95-5d78-4963-ba76-253024f6ea16) one of the reasons for the postponement of flight tests of the 15A28 missile of the Sarmat missile system, also referred to under the codes “product 001” and “subject 001”, is indicated. Recall that despite the numerous statements of the highest officials, flight tests of this complex have not yet begun. Spoiler alert: the killer butler was assigned the backwardness of the domestic element base and Western sanctions.

From the materials of the cases it follows that the developer of the control system "Sarmat" is JSC "NPO Automatics named after academician N.A. Semikhatov "(hereinafter NPOA). In turn, NPOA ordered the Scientific Research Institute of Command Instruments JSC (hereinafter NII KP) to carry out R&D for the manufacture of a complex of command devices (KKP) and a block of angular rate sensors (RCS), about which the parties entered into an agreement No. 2 / 2-1030 -15 / 787 / Yur. 765 dated 06/02/2015.

This agreement is divided into 12 stages, stages Nos. 1,3,5,7,9,11 provide for the manufacture and delivery of KKP; Nos. 2,4,6,8,10,12 - production and delivery of the ODUS. Thus, NII KP was supposed to manufacture and supply 6 sets of KKP and BDUS for missiles for flight tests (LI products). Some initial dates are mentioned:

stage 5 - 12/31/2016;

for stage 6 - 12/31/2016;

for stage 7 - 03/31/2017;

for stage 8 - 03/31/2017;

for stage 9 - 06/30/2017;

for stage 10 - 06/30/2017.

The original deadlines for the delivery of stages were repeatedly disrupted and postponed by additional agreements to the contract. So, by additional agreement No. 14 of 04.24.2019, the deadline for the execution of stage 5 was postponed to August 2019, the deadline for the execution of stage 6 was postponed to September 2019, and these deadlines were also disrupted - the shipment of the PSC for the 5th stage occurred on November 16, 2019, but the delivered PAC did not pass the entrance control at NPOA and was not accepted by it. The files mention a lot of letters, research reports and conclusions about the need to revise and restore the CCP. As a result, the obligations under the 5th stage of the SRI KP fulfilled only on 04/12/2020, and the deadline for the 6th stage was once again postponed by additional agreement No. 18 from 02/03/2020, now to 02/26/2020, by the same agreement the deadline for the 11th stage was postponed to 11/15/2020.

At the time of the court proceedings, the Research Institute of KP manufactured 3 sets of command devices for completing items LI No. 1,2,3 (stages No. 6,7,8) and a backlog was formed for LI items No. 4,5,6 (stages No. 9,10,11 ). As one of the reasons for the postponement, NII KP refers to the fact that when testing electronic products after the development of design documentation, it became necessary to purchase additional elements of the electronic base (i.e., it was necessary to replace part of the elements - note of the channel). Given the lack of competition in the market for these elements (including due to the imposed sanctions against the Russian Federation), their acquisition required significant time costs, which ultimately led to a delay in the execution of work.

Due to the unsatisfactory progress of work, the parties on 06/09/2020 agree on a joint decision:

"In the course of developing a set of command devices for the gearbox INAYA.402113.130 according to the technical assignment for the midrange of the ROC" Development of a complex of command devices for the control system equipment on the topic "001", accuracy characteristics were achieved with deviations from individual requirements of the technical specifications for the complex of command devices.

Deviations of the achieved characteristics from the requirements of the technical specifications for the complex of command devices are due to the lack of a domestic element base with the necessary characteristics.

Bringing these characteristics to the specified technical specifications for the development of a complex of command devices is possible subject to the development and implementation of an improved domestic element base no earlier than 2022yes. "- in other words, if the improvement of the domestic elemental base does not happen, then the characteristics of the KKP will not be brought up to the initial specifications, either in 2022 or later.


By the same decision, the parties established a number of measures and joint actions for the earliest possible completion of work:

"1. To allow the set of command devices with the achieved characteristics up to GLI 1-3, for which JSC" GRTs Makeeva ", JSC" NPO avtomatiki ", JSC" Research Institute of Command Devices "correct the terms of reference for the set of command devices and the corresponding documentation.

2. JSC "Research Institute of Command Devices" to develop and agree with JSC "NPO Avtomatiki", JSC "GRTs Makeeva", Federal State Unitary Enterprise "4TSNII" MO and DOGOZ, a schedule for introducing a complex of command devices to the level specified by the technical assignment for the development of the KKP.

3. JSC NPO Avtomatiki, JSC GRTs Makeeva, JSC Scientific Research Institute of Command Devices, together with FSUE 4TSNII MO and DOGOZ, make a separate decision on finalizing the complex of command devices and the necessary methods in terms of confirming the main characteristics based on the results of the implementation of cl. 2 of this solution and the results of GLI 1-3.

4. Work on this decision shall be carried out without increasing the cost of the development work. "

Further, JSC "GRTs Makeeva", the main executor of the state contract for "Sarmat", sends the NII KP letter No. 147/1131 dated 04/26/2021 with an attachment in the form of a decision on the procedure for ground-based experimental testing of on-board equipment of the control system. In accordance with the specified decision, the products supplied under the contract are approved for flight tests, taking into account the achieved characteristics (i.e., with a KKP that does not fully meet the initial requirements of the technical specification - approx. Channel). For this reason, the position of the NII KP is as follows: it is not possible to carry out work on stage 11 of the contract until the completion of flight tests. Moreover, according to the additional agreement No. 30 of 08/13/2021, concluded by the parties, the work on stages No. 9 and No. 10 is excluded from the scope of work under contract No. 1118187311572010101000282/2 / 2-1030-15 / 787 / legal 765 dated 06.02.2015 and included in the scope of work under contract No. 1118187311572010101000282/24 / 2-1030-21 / 785 / jur.2051 dated 13.08.2021 under stages No. 1 and No. 2.


Yours Missiles Underground
To be continued

среда, 5 января 2022 г.

And about Sarmat ICBM (part I)

 When we talk about the failure of flight test plans for the new 15A28 “Sarmat” heavy liquid-propellant intercontinental ballistic missile the first thing that comes to mind is that the industry did not issue flight samples of the missile for testing. Is this possible?


The main developer of the 15A28 "Sarmat" ICBM is the Makeev State Rockets Center from Miass (Ural). Accordingly, the main cooperation for the creation of a rocket looks like this:
  • complex, rocket - SRC named after Makeev (Miass)
  • rocket production - PA Krasmash (Krasnoyarsk)
  • missile control system - Scientific and Production Center of Automation and Instrumentation named after Academician Pilyugin (I must to correct this later)
  • the stage of breeding warheads and the actual warheads - NPO Mashinostroyenia (Reutov) in conjunction with the Makeev State Regional Center
  • 1st stage engines - development - NPO Energomash named after academician Glushko, production - Proton-PM
  • 2nd stage engines - presumably Design Bureau of Chemical Automatics
  • solid fuel generators and probably PAD - FTsDT "Soyuz"
  • launch facility - design bureau of special mechanical engineering
  • TPK - JSC "Avangard"
  • transport and transport-loading units - Central Design Bureau of Transport Engineering and Design Bureau "Motor" TSENKI.

 It should be noted that for all the participants in the cooperation, the entire Sarmat project in modern conditions is a new and rather difficult test. The experience that was gained by the participants of the cooperation during the Soviet era when working with the R-36M2 Voevoda missiles of this class has probably already been lost either partially or completely. It is quite possible that problems are possible at many stages of cooperation - this was very clearly seen when the production cooperation of the Bulava sea ballistic missile was put together. And, by the way, it is quite possible that in the case of “Sarmat” the level of control of components is noticeably higher - this is what caused a noticeable shift to the right of the start of flight tests. In theory, this should also ensure trouble-free missile launches during the flight test program.

Are there any problems with mass production of missiles for flight tests at PA Krasmash? Quite possibly. It seems that at least 6 missiles samples (L1-L6) should be prepared for flight tests. Nevertheless, in the footage of the chronicle from the final assembly of Sarmat ICBMs at Krasmash for August 2021, we do not see a single missile.





The assembly building for new ICBMs was built in record time in 2019-2020. - a modern and clean workshop for the final assembly of the new heavy Sarmat missiles. Back in April 2019, there were the backyards of Krasmash, and in June 2019, a new workshop was already under construction.


The territory of "Krasmash" where the workshop for the final assembly of the "Sarmat" ICBMs is located in 2013 - before the production modernization program began at the plant.



       


In April 2019, work is already planned at the site of the future workshop, but in fact they began only in May-June 2019.





The construction of the new workshop by the end of 2019 was in full swing.




The roof was closed by April 2020. And finally, by the end of 2020, the shop was completed.

It can be assumed that in 2021 Krasmash completed the workshop equipment and began assembling flight samples of Sarmat missiles, but did not manage to complete the assembly of the first missiles by the end of autumn 2021.

By the way, earlier in 2016 at Krasmash, the rearmament of production had already been “completed”, which was one of the reasons for the delay in the Sarmat's launch launches, according to the Russian media. In the course of that rearmament, Krasmash probably received new instrumental systems for high-tech processing of parts for future 15A28 missiles. As of 2015, it was planned to complete all the reconstruction and re-equipment of production at Krasmash by 2019.


Elements of 15A28 "Sarmat" throw missiles in the shops of "Krasmash" (2016)


In general, of course, there could be delays due to problems with the assembly of missiles, but components that are produced by other members of the cooperation - not Krasmash, are used to assemble the missiles. And of course there are many risks. Although, of course, the risks should have been minimal - in the components of the Sarmat rocket, many systems originate in the constituent parts of the Voevoda. It seems this was supposed to reduce the riskiness of the project.

Yours Missiles Underground
To be continued








четверг, 13 августа 2020 г.

SS-X-30 SARMAT - RS-28 Sarmat

SS-X-30 SARMAT - RS-28 Sarmat
complex 15P128 or 15P228, missile 15A28


upd.11/09/2020

Heavy liquide intercontinental ballistic missile - missile for replacement of the RS-20 / R-36 / SS-18 SATAN ICBMs. 

Launch tube with ejection-test version of ICBM RS-28 Sarmat (test-site Plesetsk before launch 27.12.2017, http://mil.ru)



























Developers:
- Makeev GRTs (State Rocket Center, Miass, the lead developer)
- NPO Mashinostroyenia (Reutov)
- NPO Energomash (engines)
- KBSM (launch equipment)
Some of reserchers had idea about possibility of cooperation with Yuzhnoye Design Bureau (Dnepropetrovsk, Ukraine) - it was possible before 2014.

Developing: first information about development of Sarmat was published at 2009. The terms of reference for the development of ICBMs was approved in 2011 and the technical development for the "Sarmat" was begin in 2012.

Tests: first ICBM Sarmat for ejection tests was ready from industry at november 2015 but with several different reasons first launch was delayed to 2017 - engines, truobles with pant, not ready test-site. Media wrote in 2017 that to the end of year plant must build three missiles for ejection tests.   

Launchs list of Sarmat missile:
01-ejection - First ejection test (one of three) - mod. RS-28 Sarmat for ejection tests - test-site Plesetsk Yubileynaya site (silo) - 27.12.2017
history of plans (special feature of russian planning):
june 2015 (early 2015)
autumn 2015 (26.06.2015)
17-31.12.2015 (16.12.2015)
march 2016 (january 2016)
april-june 2016 (20.02.2016)
second half 2016 (11.05.2016)
march-april 2017 (13.01.2017)
end of june 2017 (01.04.2017)
october-december 2017 (october 2017)

02-ejection - Second ejection test (two of three) - mod. RS-28 Sarmat for ejection tests - test-site Plesetsk Yubileynaya site (silo) - 29.03.2018

03-ejection - Third ejection test (three of three) - mod. RS-28 Sarmat for ejection tests - test-site Plesetsk Yubileynaya site (silo) - may 2018 (ref).

01 - First flight test - real RS-28 mod. - test-site Plesetsk Yubileynaya site (silo) - not now (august 2020)
history of plans (special feature of russian planning):
first half 2016 (2015)
second half 2016 (20.02.2016 г.)
forecast - 2017-2018 (12.05.2016 г.)
forecast - 2018 (07.09.2016)
forecast - 2019-2020 (2018) 
forecast - end of 2020 (2020)


Yubileynaya test-site at Plesetsk with process of loading Sarmat at his silo


Production of Sarmat missiles was established at main plant of Makeev produce cooperation - Krasnoyarsk Machinebuilding Plant. Contract to produce firsts Sarmats was begin in 2011. And in 2014 production was begin.

Employment of Sarmat ICBM will begin at 2021 at Uzhur (Krasnoyarsk region) RVSN division (as we know now at 2020) and later at Dombarovsky. But in 2015 they said about employment in 2018. My forecast for now - 2023-2025. 

19.11.2019 Ru MoD said that all works for emplayment will be finished at 2021 (ref).

Launch equipment: silo launch complex 15P728 similar to silo compexes for heavy ICBMs like R-36M / R-36M2 SATAN. Developer - KBSM.

Transportation-loading vehicle 15T526. Developer - KB Motor TsENKI.

Upper part of transport-launch tube of Sarmat ICBM

Reloading ICBM Sarmat from train to transportation vehicle 

Transportation-loading vehicle 15T526

Missile 15A28 Sarmat
Three stages missile with liquide engines. At first stage used engine similar to 15D285 for SATAN ICBM. Similar liquide engines used at second and third stages.


Guidance: autonomic inertial guidance system with most modern hyroscop system.

Technical data of Sarmat missle:
Length - 32 m
Diameter - 3 m
Start weight - 200 000 kg
Payload weight - 10 000 kg (with upper stage for MIRV/MARV)
Range - 11 000 km
CEP - 100-150 m

Payload:
1. 10-15 MIRV's with several devices of anti-ABM complex
2. 3-5 MARV like object 4202 / 15Yu71












First ejection launch of Sarmat missile at Plesetsk, 27.12.2017.










Second ejection launch of Sarmat ICBM, Plesetsk, 29.03.2018


Main special source Militaryrussia.ru - thank you!
Yours Missiles Underground

понедельник, 10 августа 2020 г.

Russian ICBM staff (2020)

 Russian ICBM staff (2020)

Estimation staff of russian ICBM at the end of 2020

R-36M2 SATAN - 46 missiles (each 10 middle MIRV)
RS-12M Topol - 27 TEL with missiles (mono RV)
RS-12M1 Topol-M - 18 TEL with missiles (mono RV 1Mt-class)
RS-12M2 Topol-M (silo) - 60 missiles (mono RV 1Mt-class)
RS-24 Yars - 101 TEL with missiles (each 6 light MIRV)
RS-24 Yars (silo) - 18 missiles (each 6 light MIRV)
RS-24 Yars-S - 32 TEL with missiles (each 3 middle MIRV)
UR-100HUTTkH Avangard - 2-3 missiles with type 4202 AGBO



Yours Missiles Underground

пятница, 7 августа 2020 г.

Yars designation

First post from new military blog "Missiles Underground". We will write about modern missiles systems - russian and other. But most of russian. And lets begin...

Yars designation

Russian mobie ICBM Yars have several modification

1. First mobile model Yars (Topol-MR) - SS-29 or SS-27 mod.2 SICKLE-B - name of complex 15P155M, name of TEL - 15U175M, missile - 15Zh55M, name for INF-treaty RS-12M2R, auto base is MZKT-79221. Base digits 55M because 55 was base digits for Topol-M / Universal missiles and Yars is MIRV-mod of Topol-M.

2. Second mobile mod. Yars-S with middle-class N-warheads and new equipment - name of complex 15P155M1, name of TEL - 15U175M1, missile - 15Zh55M1, name for INF-treaty RS-12M2R1, autobase is MZKT-79221. 

3. Third mobile mod. Yars-M (not in service on 2020, only tested) - new missile probably with separate engine for each MIRV - name of complex 15P180, name of TEL - 15U200 (?), missile - 15Zh80.

Also they had three silo-mod of Yars with similar warheads ability:

1. Yars - name of complex 15P165M, name of launch system - 15P765M, missile - 15Zh65M, name for INF-treaty RS-12M2R.

2. Yars-S - name of complex 15P165M1, name of launch system - 15P765M1, missile - 15Zh65M1, name for INF-treaty RS-12M2R1.

3. Yars-M - name of complex 15P181, name of launch system - 15P781 (?), missile - 15Zh81.

That's all for now about Yars.

Yours Missiles Underground

And about Sarmat (part II)

Engines According to the already known data on the Sarmat rocket, the development of engines for the first stage is carried out by NPO Energ...